A. An approval may be modified at any time after a decision becomes final.

B. Modification Review Procedures.

1. A modification that does not have significant additional impacts on surrounding properties must be reviewed only under the criteria applicable to the aspect(s) of the proposal that are to be modified.

2. A modification that has significant additional impacts on surrounding properties must be reviewed under all criteria applicable to the entire approval and may, at the discretion of the City, require the filing of a new application.

3. A modification must not be considered to have significant additional impacts on surrounding properties if the identified impacts could be addressed under the applicable provisions of this code at the time of future development (e.g., a future site plan review or conditional use permit application).

4. A modification that is a new proposal must be filed as a new application.

C. An application for a modification of a Type I approval must be processed as a Type I application. All other modifications must be processed as a Type II application unless elevated to a Type III process by the Community and Economic Development Director.

D. The original approval time limitation is governed by BDC 4.1.1310.

E. Modifications of development approvals must meet the approval criteria required in subsection (B) of this section in the appropriate corresponding section of this code (e.g., modification of a site plan review approval is subject to BDC Chapter 4.2; modification of a conditional use permit is subject to BDC Chapter 4.4, modification of a master plan, area plan or special planned district is subject to the applicable sections in BDC Chapter 4.5). For modifications of a master plan, PUD or special planned district approved under land use regulations in place prior to April 14, 2017, see subsection (F) of this section.

F. Modifications of a master plan, PUD or special planned district approved under land use regulations in place prior to April 14, 2017, must meet the approval criteria required in subsection (B) of this section in one of the following sections in BDC Chapter 4.5, Master Plans:

1. The modification of a master plan, PUD or special planned district that is primarily for residential uses is subject to the applicable approval criteria in BDC 4.5.200(D).

2. The modification of a master plan, PUD or special planned district that is primarily for institutional uses is subject to the applicable approval criteria in BDC 4.5.300(E).

3. The modification of a master plan, PUD or special planned district that is primarily for employment uses is subject to the applicable approval criteria in BDC 4.5.400(D). [Ord. NS-2445, 2022; Ord. NS-2434, 2022; Ord. NS-2405, 2021; Ord. NS-2303, 2018; Ord. NS-2289, 2017; Ord. NS-2251, 2015; Ord. NS-2229, 2014; Ord. NS-2122, 2009; Ord. NS-2016, 2006]