A. Applicability. The following Transportation Mitigation Plan applies to all development within the Parkside Place Master Planned District. The Transportation Mitigation Plan is adopted and implemented pursuant to BDC 4.7.600(D)(1).

B. Alternate Transportation Design Standards. Transportation facilities within the Parkside Place Master Planned District must comply with the standards set forth in BDC 2.7.4650.

C. Transportation Mitigation. The following transportation mitigation measures must be constructed pursuant to the deadlines set forth in Table 2.7.4660 below.

Table 2.7.4660

Mitigation Requirements

Trigger

The COID canal must be piped when it is within a City of Bend right-of-way. The COID pipe north of the O’Connor right-of-way must be located to allow for a potential Highway 20 undercrossing of the Bend Park and Recreation trail

Prior to final plat of the property containing the multi-unit development

Coordinate with CET for a bus route to the site. If a bus stop is desired by CET, one must be constructed at a location determined by CET prior to the final plat containing the transit stop location

Coordination must occur prior to platting of properties south of Livingston Drive. The bus stop must be constructed prior to the final plat of the phase containing the bus stop location.

Complete the sidewalk connection within Livingston Drive to 27th Street

Prior to final plat of the initial project phase

A pump station is required at the eastern property line. If applicable, a temporary road must be constructed over the main to the pump station for operations and maintenance

Prior to final plat of the initial project phase

If a raised median is not installed within Highway 20 by ODOT, a raised porkchop must be installed at the intersection of the north-south collector with Highway 20

Prior to final plat of the initial project phase

The Bend Parks and Recreation Big Sky Park path must be constructed from Bear Creek Road north along the COID canal to Highway 20

Prior to final plat of each phase containing the trail alignment

[Ord. NS-2466, 2023]