A. Applicability. The following Transportation Mitigation Plan applies to all development within the Talline Master Planned District.

B. Alternate Transportation Design Standards. Transportation facilities within the Talline Master Planned District must comply with the standards set forth in BDC 2.7.4470 and Figure 2.7.4470.

C. Transportation Mitigation. The following transportation mitigation measures must be constructed pursuant to the schedule set forth in the Westside Infrastructure Group Development Agreement (Ordinance NS-2316), summarized in Table 2.7.4480.

Table 2.7.4480. Transportation Mitigation

Mitigation Requirement

Trigger

Dedicate NW Shevlin Park Road right-of-way and construct a single-lane asphalt roundabout at Skyline Ranch Road and Shevlin Park Road

Prior to platting or improvement of lots that represent 237 p.m. peak hour trips

Construct Regency Street to the Neighborhood Collector section in Table 2.7.4470 from its current improved terminus to the Master Plan boundary (±850 feet).

Prior to platting of the phase that includes the segment of Regency Street intersecting the eastern boundary of the Talline Master Plan

[Ord. NS-2440, 2022]